Public Notice - Surf Road Paving Project Timeline

PUBLIC NOTICE
Surf Road Paving Project Timeline

The Wakulla County Road & Bridge Department reports that turnouts are being paved along Surf Road in preparation for the mainline paving project. This work is expected to be completed tomorrow, August 24, 2022. Mainline paving of Surf Road will begin Monday, August 29, 2022, and is expected to be completed by Friday, September 2, 2022. Travelers can expect to encounter one-way traffic in active work areas throughout the duration of the mainline paving project.
 
The dates above are estimates and are contingent upon adequate weather conditions and the availability of resources, any adjustments to the schedule will be noticed to the public. To contact the Road & Bridge Department, please call 850-926-7616.